CB1 Meeting 4-10-18
This presentation is a study overview, summary of recommendations and implementation proposals for three street direction changes. Presented to the Bk Community Board 1 on April 10, 2018.
Existing Conditions Analysis
This presentation was given to the public on 3/30/2017 at the Swinging 60s Senior Center. It contains details from the existing conditions analysis on the subjects of demographics, land use, traffic, pedestrians, bikes, trucks, transit and safety as well as a summary of community feedback and potential improvement locations.
Kickoff Presentation
This document was presented on 5/12/16 and 5/16/16 to the public. It includes the study goals and objectives, study area, timeline and subjects of analysis.
2019 SIP Presentation to CB1 Transportation Committee
This presentation was given 4/4/19 to Community Board 1 Transportation Committee and details three projects from the study at the following locations:

* Flushing Avenue @ Varick St
* Broadway @ Boerum St
* Flushing Ave between Humboldt St and Bushwick Ave
Study Recommendations - 6-7-18
This presentation includes the study goals and process, a summary of the existing conditions findings and the full study recommendations presented at P.S. 84 (250 Berry St) on 6/7/18.
CB1 Transportation Board Presentation - 5/31/18
This document was presented on 5/31/18 to the CB1 Transportation Committee. It further describes the street conversions of Eckford St and North Henry and is a continued discussion of the Full Board presentation from April 10, 2018